Home / Casita plans / 450 sq ft pitched-roof

Albuquerque, New Mexico

450 sq ft casita
with a single-pitch metal roof

The smallest of the city's pre-approved plans and the fastest to build. One open room, with a full-width glass wall onto the porch that makes it feel bigger than it is.

A standing-seam metal shed roof with a deep front overhang and a continuous band of clerestory glass under the high side. More daylight and more shade, for a little more money.

Call Ruelas Construction

505-777-7777

Licensed, bonded, insured. Serving New Mexico for over 30 years.

Alma 450 sq ft 25' × 18'

The number

What this plan costs to build.

Every dollar below traces to a line item, anchored to a June 2026 Albuquerque contractor quote instead of a national average. The city gives the drawings away, so the design fee most builders charge is not in here.

All in, on an easy lot $116,904 Design, permits, construction, and contingency. About $260 per finished square foot.
On a harder lot $137,964 A long utility run, a new sewer connection, a tight gate, a slope, and an old slab to clear. Most lots land between the two.

The five lot questions move this number more than anything else, and a website can't answer them for you. The configurator asks them and reprices as you go.

The plan

What's inside 450 square feet.

  • Open living / sleeping / kitchenette
  • Full bath with tub-shower
  • Stacked laundry closet

Specifications

Plan450 sq ft, single-pitch metal
DrawingsFree, published by the city
Plan reviewPre-approved, structural review skipped
Heated area450 sq ft
Footprint25' × 18'
SleepsStudio
Bathrooms1
Roof styleModern territorial
Shell rate$165 per sq ft

Permit to keys

How long this takes.

01
Design and site plan

Pick a plan, walk the lot, and get the plot plan and grading drawings drawn against the pre-approved set.

2 to 4 weeks
02
Permit

Site Plan - Administrative review, public notice, then the building permit through ABQ-PLAN. Pre-approved plans skip the structural review that eats most of this window.

4 to 10 weeks
03
Site work and foundation

Clear, trench the utility run, form and pour the monolithic slab.

2 to 3 weeks
04
Frame, dry-in, rough-ins

2×6 walls at 16" on center, roof, windows and doors, then the trades.

4 to 6 weeks
05
Finishes

Insulation, drywall, stucco, cabinets, floors, fixtures, paint.

5 to 7 weeks
06
Inspections and keys

Final inspections, certificate of occupancy, walkthrough.

1 to 2 weeks

City rules

What Albuquerque requires.

These apply to every casita on a residential lot, not just this plan. Check your own parcel on the city zone map before anything else.

750 sq ft maximum650 sq ft inside the Downtown CPO-3 area.
One casita per lotAnd it has to sit behind the rear wall of the main house.
5 foot setbacksSide and rear. Corner lots match the main house street setback.
No taller than the main houseHeight is capped by whatever is already on the lot.
R-A, R-1, R-T, and R-ML zonesCheck your parcel on the city zone map before anything else.
One off-street parking spaceAn existing spare space counts.
25% yard coverage capThe casita cannot cover more than a quarter of the side and rear yard.
Exterior has to match the houseColor has to match or closely resemble the main dwelling.